About Us

Background

 

The 600MW Monsoon Wind Power Project is a landmark initiative under construction, featuring a 500KV transmission line linking Laos to Vietnam, and is planned to be completed by 2025. As the first wind farm in Laos and the largest in Southeast Asia, Monsoon set a new benchmark by establishing a bankable cross-border Power Purchase Agreement. Beyond providing green energy, Monsoon also aims to uplift local communities through its comprehensive community development program. The project aspires to become the most cost-effective renewable energy model in ASEAN, aligned with the ASEAN Grid vision, while enhancing regional connectivity and advancing the green energy transition across Southeast Asia.

Key
Milestones

arrow left
2011
2025
arrow right
arrow left
arrow right

November 2011

MOU executed between GOL and IEA, granting IEA exclusive rights to develop a large-scale wind farm in central and southern Lao PDR, including Sekong Province.

July 2012

Wind monitoring began in Dak Cheung District, Sekong, supported by an international wind consultant.

August 2015

Based on the preliminary feasibility study, IEA identified Dak Cheung District in Sekong and Sanxay District in Attapeu as the most promising locations for a large-scale wind project. The Project Development Agreement executed between GOL and IEA confirmed IEA's exclusive rights to develop the Monsoon Wind Power Project.

October 2016

MOU between Governments of Lao PDR and Vietnam for supply of 5,000MW renewable power from Lao PDR to Vietnam

July 2017

The GOL offered the project's electricity generation to Vietnam via a "Nomination Letter," which Vietnam formally accepted under the 5,000MW on energy sector cooperation between Lao PDR and Vietnam.

May 2018

The draft Environmental, Social, and Health Impact Assessment was submitted to the Ministry of Natural Resources and Environment (MONRE) for approval after successful consultations with villages and the provincial GOL. Meanwhile, IEA worked with the Institute of Energy of Vietnam to conduct the Grid Impact Study and identify potential connection points to the Vietnam grid.

September 2019

The Grid Impact Study was approved by Vietnam Electricity (EVN) and the Ministry of Industry and Trade (MOIT), confirming the project’s connection at 500 kV at the Thanh My Substation in Quang Nam Province, with no negative impacts on the Vietnam grid.

Following EVN’s approval, the Tariff MOU was signed, and IEA began PPA discussions with EVN. IEA also initiated discussions with the central government on the power import approval process.

 

July 2020

After approval from relevant ministries, the Prime Minister of Vietnam authorized the import of power from the project, including the required 500 kV transmission line in Vietnam’s Power Development Plan.

An international environmental and social consultant was also engaged to ensure compliance with international lenders’ safeguard policies.

July 2021

PPA signed with EVN.

January 2022: Amended and restated PPA signed with EVN.

May 2022: The international ESHIA was successfully disclosed on the Asian Development Bank’s website. 

November 2022: Turnkey EPC Contract signed with POWERCHINA.

December 2022: Concession Agreement signed with GOL for the first wind farm in Lao PDR.

March 2023: Monsoon signed a $692.55 million non-recourse project financing package with lenders.

March 2023: Construction of Monsoon Wind began.

July 2023: First set of wind turbines arrived at the site.

October 2023: First wind turbine installed.

September 2024: 100 wind turbine generators (WTGs) installed.

Target to complete commercial operations.

Project Site

 

The Project is located in the Dak Cheung district of Sekong province and the Sanxay district of Attapeu province. It sits on the Dak Cheung Plateau, with elevations between 1,100 m and 1,700 m above sea level and features moderate to complex terrain. The area mainly consists of rolling forested land, farmland, and local villages.

Access to the Project is via Route No. 16B, an economic route connecting Thailand, Laos, and Vietnam. The distance from Sekong town in Lamam district to the Project area is about 60 km.

Facts and Figures

950
M USD total Project cost
27
km Transmission Line from substation to Lao-Vietnam border
200+
Dedicated Team Members
10+
Years of wind measurement
133
Wind Turbine Generators
110
Hub Height
250
ha of Permanent Land Use
25
Years of Power Purchase Agreement
28
Years of Concession Agreement
meet the team_monsoon wind.jpg

Our Leaders

Nat (2).png

Nat Hutanuwatr

Managing Director

peter.png

Peter Littlewood

Program Director

Narut (2).png

Narut Boakajorn

Project Development Director & General Manager

Itthipol.png

Itthipol Kanjanaphan

Project Director

Jeremy 1.png

Jeremy Warman

Deputy Project Director & Commissioning Manager

Varawuth.png

Varawuth Jaidchaya

Construction Manager

Amorn.png

Amorn Vorashompoo

Deputy Commissioning Manager

Siripoom Warathanasin.png

Siripoom Warathanasin

Environmental & Social Manager

Chaovalit.png

Chaovalit Khunchaiyaphum

Local Government Liaison & Community Development Lead

Supamas 1.png

Supamas Rattanalapon

Accounting and Treasury Lead

Zam-removebg-preview.png

Zamanta Legados

Project Finance Lead

Pimpida.png

Pimpida Punnakanta

HR, Administration & Logistic Lead

Parichat.png

Parichat Thanapatpaiboon

Commercial Advisor

Giang.png

Nguyen Truong Giang

Representative - Vietnam

Vinh.png

Nguyen The Vinh

Representative - Vietnam

Sarawut.png

Sorawut Pairojkul

Project Control Manager

Tou.png

Xaythinanh Philamakhot

Procurement Manager

Arkom Y. 1.png

Arkom Yuangyai

Engineering Manager

Apirat Sansabai 1.png

Apirat Sansabai

Civil Manager

Phisit 1.png

Phisit Silaoon

Government & Community Liaison Manager

Hendra 1.png

Hendra Winastu

Biodiversity Manager

Heuvang Pangtong 1.png

Heuvang Pangtong

Environmental Manager

Chakrit 1.png

Chakrit Duangjai

Social and Labor Manager

Lai Van Uoc 1.png

Lai Van Uoc

Safety Manager

Ouwab square.jpg

Patrapol Tangchitnamthamrong

Commercial Manager

Sira Khamklai.png

Sira Khamklai

Interim O&M Manager

Weerapong-removebg-preview 2.png

Weerapong Rattanamontienchai

Human Resource & Site Office Manager

Dee-removebg-preview 1.png

Youa Ye Xiong Wa-Kai

Accounting and Treasury Manager

Tina.jpg

Danouphim Ounalom

Office Manager

Wattanee (2).png

Wattanee Prungchaiyaphum

Corporate Secretary

Kritawit.png

Kritawit Sriwattanpan

GOL Coordinator & Project Management

Bee.png

Vilasouk Sisoulath

GOL Coordinator & Project Management